The bearings arrived nearly a week earlier than expected.
So where to start, sheaves or straps? I seem to have material for both, so it really doesn't matter. Straps it is then.
10mm M.S. plate, four pieces. In some ways I would have preferred brass but 10mm is NOT cheap, and it wasn't in stock! I thought about Dietrich, and doing them in one hit, but discretion said, do it in two. I don't trust the stiffness of the mill with such a long cutter. Just call me windy!

I hate the swarf that comes off the cutter when doing these side on cuts, it is just millions of tiny needles, I'm still picking them out of places I didn't know I had places!